NETWORKDAYS
function NETWORKDAYS(arg1: any = null, arg2: any = null, arg3: any = null): number | string | boolean
Description
Returns the number of whole workdays between two dates.
Parameters
- arg1
any
null Is a serial date number that represents the start date.
- arg2
any
null Is a serial date number that represents the end date.
- arg3
any
null Is an optional set of one or more serial date numbers to exclude from the working calendar, such as state and federal holidays and floating holidays.
Returns
number | string | boolean
Try It
const oWorksheet = Api.GetActiveSheet();
var oFunction = Api.GetWorksheetFunction();
var ans = oFunction.NETWORKDAYS("3/16/2018", "12/31/2018");
oWorksheet.GetRange("C1").SetValue(ans);